Renovation Cost Calculator for a New-Build Apartment in Armenia

New-build apartments in Armenia are sold in black- or white-frame condition, leaving the buyer to complete the finishes. Enter the area, starting condition and finish level to estimate the total and per-square-metre cost of making the apartment move-in ready.

  • Updated August 2026
  • Yerevan market
  • Free · no sign-up

Currency

What state is the apartment in now?

Finish level

The owner-occupier standard: mid-range imported tiles and laminate, stretch ceilings with LED recesses, branded taps and quality doors.

20 m²500 m²

Total floor area from the purchase contract, balconies included.

Living room plus bedrooms. Kitchen and bathrooms are counted separately.

Bathrooms have the highest cost per square metre in the apartment.

m
2.2 m4.5 m

Only work linked to wall height changes: partitions, plaster, paint and the ceiling perimeter.

Add-ons1 selected · ֏1,600,000
%
0%30%

10–15% is the usual rule of thumb, closer to 20% if walls or wet rooms are moving.

Estimated renovation cost

֏12,940,400

֏161,755 per m² · About 16 weeks

Planning range ֏10,611,128 – ֏15,269,672

Estimate. Not a quote.

Core works
֏10,164,000

15 lines

Add-ons
֏1,600,000

1 selected

Contingency (10%)
֏1,176,400

On top of the subtotal

Materials vs labour
57% / 43%

֏6,743,680 · ֏5,020,320

Where the money goes

Each line is calculated per square metre, room, bathroom or opening, then rounded once, so the breakdown adds up exactly to the headline figure.

  • Bathroom fit-out (waterproofing, tiling, sanitary ware)
  • Wall finishes (filler, primer, paint or wallpaper)
  • Wall levelling & gypsum plaster
  • Floor coverings (laminate / parquet / tile)
  • Heating & ventilation (gas boiler, radiators)
  • Ceilings (stretch or suspended plasterboard)
  • Contingency ֏1,176,400

Each block shows one line of work as a share of the ֏12,940,400 overall cost. The percentages use that same total, including contingency.

Core works

  • Bathroom fit-out (waterproofing, tiling, sanitary ware)

    Materials ֏812,500 · Labour ֏437,500

    ֏1,250,0009.7%
  • Wall finishes (filler, primer, paint or wallpaper)

    Materials ֏420,000 · Labour ֏780,000

    ֏1,200,0009.3%
  • Wall levelling & gypsum plaster

    Materials ֏336,000 · Labour ֏784,000

    ֏1,120,0008.7%
  • Floor coverings (laminate / parquet / tile)

    Materials ֏643,200 · Labour ֏316,800

    ֏960,0007.4%
  • Heating & ventilation (gas boiler, radiators)

    Materials ֏572,000 · Labour ֏308,000

    ֏880,0006.8%
  • Ceilings (stretch or suspended plasterboard)

    Materials ֏324,000 · Labour ֏396,000

    ֏720,0005.6%

Add-ons

  • Fitted kitchen cabinets & worktop

    Materials ֏1,360,000 · Labour ֏240,000

    ֏1,600,00012%
Core works
֏10,164,000
Add-ons
֏1,600,000
Contingency (10%)
֏1,176,400
Total
֏12,940,400
  • Shell & structure֏2,304,00018%
  • Engineering & utilities֏2,000,00015%
  • Surfaces & finishes֏2,880,00022%
  • Fit-out֏2,780,00021%
  • Logistics & cleaning֏200,0002%
  • Add-ons֏1,600,00012%
  • Contingency֏1,176,4009%

Materials vs labour

Materials ֏6,743,680Labour ֏5,020,320

Prices checked: August 2026 · Planning estimate for Yerevan, including VAT and the contractor's margin. It excludes the purchase price, notary and registration fees, mortgage interest, and any structural, façade or common-area work.

What each finish level would cost

Same apartment, same scope, three material grades. Tap a card to switch the whole page to that level.

How long it takes

Estimated calendar time for a crew of about four people working continuously, with the phases shown in the order they occur.

  1. Design, measurement & procurement: wk 0–1.6
  2. Strip-out / partitions & setting out: wk 1.6–3.2, Spend ֏1,290,000
  3. Rough MEP: electrical, plumbing, heating: wk 3.2–6.1, Spend ֏1,640,000
  4. Plaster & floor screed (plus drying): wk 6.1–8.8, Spend ֏1,664,000
  5. Waterproofing & wet-area tiling: wk 8.8–11.2, Spend ֏1,250,000
  6. Ceilings, wall finish & flooring: wk 11.2–14.1, Spend ֏2,880,000
  7. Second fix: doors, fixtures, kitchen, AC: wk 14.1–15.4, Spend ֏2,840,000
  8. Snagging, cleaning & handover: wk 15.4–16, Spend ֏200,000

The amount beside each phase is the work allocated to it. Together, the phases make up the ֏11,764,000 subtotal. Contingency is deliberately not assigned to a phase because it has not yet been spent.

Add 15–20% to the timeline for material lead times, payment-related pauses, weekday restrictions on noisy work, and lift or delivery bookings.

Black frame and white frame: what you are actually buying

Most new-build apartments in Armenia are sold unfinished, generally as either a black frame or a white frame. A black frame («սև գործ», «черновая отделка») is a bare shell: the structure, an entrance door and utility risers reach the flat, while exterior windows may or may not be fitted. A white frame («սպիտակ գործ», «белая отделка») adds plastered walls and ceilings, a levelled floor screed, and first-fix electrical and plumbing work, leaving the surfaces ready for finishes. Neither condition is move-in ready or includes the final finishes and fixtures. For the representative 80 m² three-room flat used by this calculator, the difference is worth about a third of the bill at the same finish level. That is a large saving, although the final finishing work that dominates the total is the same in either case.

  • Starting from a black frame means paying for all fifteen work lines in this model: partitions, plaster, screed, first-fix electrics and plumbing, heating, and all the final finishes.
  • A white frame removes six of those lines: site preparation and partitions, plaster, screed, first-fix electrics and plumbing, and glazing. On 80 m² at Comfort level, the cost falls from ֏10,164,000 to ֏6,364,699, a saving of about 37%.
  • Heating is rarely included. A gas boiler, radiators and pipework cost ֏880,000 on 80 m² and remain the buyer's responsibility in almost every Yerevan pre-finish handover, so check that line carefully.
  • A «սև գործ» with the windows already fitted is the most common handover. The glazing is worth about ֏650,000 on a three-room flat, but check the balcony because it is usually priced separately from the room windows.

What the developer hands over — and what you still need to budget for

Read the finish specification annexed to your purchase contract, not the sales brochure. Developers commonly provide plastered walls, screed, glazing, an entrance door, and first-fix services to the points shown on the plan. You still need to budget for floor and wall finishes, tiling, interior doors, the kitchen, bathroom fittings, sockets, switches, light fittings, radiators or underfloor heating, and air conditioning. Specifications differ between developers and even between buildings in the same complex, so confirm in writing whether balcony glazing, meter connections and the heating boiler are included before relying on any per-square-metre estimate.

  • Ask for the annex, not the brochure, and check four items by name: balcony glazing, the gas boiler, the electricity and water meter connections, and the entrance door.
  • «Rough-in to the points shown on the plan» means cable and pipe concealed in the walls, but no fittings you can use. Sockets, switches and light fittings are a separate line: ֏4,500 per m², or ֏360,000 on an 80 m² flat.
  • Interior doors are rarely included in Armenian new-build handovers. At ֏120,000 per leaf, four doors in a three-room, one-bathroom flat add ֏480,000 that is easily missed in an initial budget.
  • Waste removal and the final deep clean are yours as well: roughly 0.15 m³ of debris per m² of floor, about 2% of the whole bill, and the single most common omission from a verbal quote.

What actually drives the cost per square metre

Four factors have the greatest effect on the estimate. First is the starting condition: a black frame still needs plaster, screed and complete first-fix services that a white frame already includes. Second are the wet rooms. Kitchens and bathrooms cost several times more per square metre than a bedroom, so a compact two-bathroom flat can cost more than a larger one-bathroom flat. Third is the material tier: the same layout can be finished to rental grade or, with imported tiles, bespoke joinery and engineered flooring, at nearly three times the cost. Fourth is whether you move walls, relocate risers, or add air conditioning and underfloor heating. Changes to building services are where budgets can quietly double.

  • Wet rooms dominate. One comfort-level bathroom is ֏1,250,000 — 12% of an 80 m² black-frame bill for about 5% of the floor — so adding a second bathroom costs ֏1,370,000 and can put a smaller flat above a larger one.
  • Walls are another major cost. Plaster, filler, primer and paint cost ֏29,000 per square metre of floor because a room with a 2.8 m ceiling has roughly three square metres of wall for every square metre of floor.
  • The finish level is the biggest single lever: the same 80 m² black-frame layout costs about 84,000 AMD/m² at Basic level and about 241,000 AMD/m² at Premium level — 2.9× as much for the same area.
  • Ceiling height matters less than many people expect. Increasing it from 2.8 m to 3.2 m adds about 4%, because only plaster, paint, partitions and the ceiling perimeter vary with height.

How to budget before you sign

Include the renovation in your purchase decision rather than budgeting for it afterwards. Use the floor area from the purchase contract, choose a realistic finish level, and add furniture and appliances as a separate line. They fall outside most contractor quotes and add roughly 40% here. Then add a contingency of 10–15%, or closer to 20% if you are moving walls or wet rooms, and keep it visible as its own line so it remains a buffer rather than becoming part of the spending target. Finally, plan cash flow across three to six months of work, remembering that many buyers pay rent and a mortgage throughout that period. A written, room-by-room scope with quantities is the single best protection against overruns.

  • Furnishings are not included in a builder's quote. The appliance and furniture packages here cost ֏4,150,000 on top of a ֏10,164,000 Comfort-level renovation — about 40% more — and a fitted kitchen with a worktop adds another ֏1,600,000.
  • Keep the contingency as its own line: 10% of that same job is ֏1,016,400. Raise it towards 20% the moment walls, wet rooms or risers are on the table.
  • Poor sequencing costs money as well as time. Choose tiles and sanitary ware before the plumber sets out the fittings; measure a custom kitchen after plastering, then order it weeks before installation; and allow for screed drying time that is rarely shown on a quote.
  • Budget for the schedule too: about 15 weeks from a black frame at Comfort level and about 11 from a white frame, plus a 15–20% allowance for lead times and weekday-only noise rules. During that whole period, you may also be paying rent.

Once you have the keys, the spending does not stop. Estimate the annual running cost too with the Property Tax Calculator.

Will you recover the renovation cost when you sell or rent?

Partly, depending on what you build. A neutral, well-executed mid-range finish tends to retain the most value on resale because it lets a buyer move in immediately and broadens the market for the flat. Personalised or premium finishes recover the smallest share because the next owner rarely pays for someone else's taste. For a rental, finish quality has much less effect on achievable rent than location, layout and floor, so durable and simple usually offers better value than expensive. Compare your finished cost per square metre with sale prices in the same district before choosing a tier. If the total exceeds the local market level, you are spending for your own quality of life rather than for an investment return.

  • Compare the finishing cost with the purchase price per m² in the same district. A Comfort finish costs about 127,000 AMD/m² from a black frame, while Premium costs about twice as much for exactly the same flat.
  • The work most likely to retain value on resale is what a buyer cannot easily redo: bathroom waterproofing and tiling, the screed, wiring and heating. These are also the most costly items to correct later.
  • Bespoke joinery, feature lighting and statement finishes tend to recover the least because buyers often see them as somebody else's taste.
  • For a flat you intend to rent out, basic-tier finishing is about two thirds the cost of comfort on the same layout, and Yerevan rents respond far more to district, floor and layout than to the grade of the laminate.

The specification is the contract, not the brochure

Handover specifications differ between developers and even between buildings in the same complex. Confirm in writing whether balcony glazing, meter connections and the heating boiler are included before you trust any per-square-metre figure.

Keep the contingency visible

Hold 10–15% on top of the agreed estimate, or closer to 20% if you plan to move walls or relocate wet rooms. Keeping it as its own line rather than folding it into the budget is what makes saying no to scope creep possible.

Most delays are not construction delays

They come from late material decisions, lead times on custom kitchens and joinery, and building rules that restrict noisy work to weekday hours. Many buyers pay rent and a mortgage at the same time for several months, so plan your cash flow accordingly.

FAQ

Frequently asked questions about renovating a new apartment in Armenia

What black-frame and white-frame handovers include, how much renovation costs per square metre at 2026 Yerevan prices, and how long the work takes.

A black frame apartment («սև գործ», «черновая отделка») is handed over as a bare shell: structural walls and an entrance door, with utility risers reaching the flat but no internal distribution, partitions, plaster or screed. Many Yerevan developers provide a black frame with exterior windows already fitted, saving about ֏650,000 on a three-room flat, so confirm which version you are buying. A white frame apartment («սպիտակ գործ», «белая отделка») adds plastered walls, a levelled floor screed, glazing, and first-fix electrical and plumbing work, leaving surfaces ready for finishes. In both cases, the buyer still pays for flooring, tiling, interior doors, the kitchen, sanitary ware, sockets and light fittings, and usually the gas boiler as well.
Renovation in Yerevan is quoted per square metre. This calculator's rates put a typical 60–100 m² flat starting from a black frame at roughly 81,000–89,000 AMD/m² (about USD 220–245) for a Basic, rental-grade finish; 123,000–134,000 AMD/m² (about USD 335–370) for a Comfort, owner-occupier finish; and 233,000–255,000 AMD/m² (about USD 635–700) for Premium, design-led work. For the representative 80 m² three-room flat, that is ֏6,708,240, ֏10,164,000 and ֏19,311,600 — USD 229, 347 and 659 per m². Starting from a white frame reduces the cost by about a third, to roughly USD 135–155, USD 205–240 and USD 390–450 per m², because plaster, screed, glazing and first-fix electrics and plumbing are already complete, although the gas boiler and radiators usually are not. These figures cover only the construction work: labour, materials, VAT and the contractor's margin, with no contingency. Furniture and appliances together add roughly another 40%, and a fitted kitchen about 15%; structural, façade and common-area work is also excluded.
A white-frame handover typically includes plastered or skim-coated walls and ceilings, a levelled floor screed, exterior windows and balcony glazing, an entrance door, and first-fix electricity, water and drainage to the points marked on the plan. The calculator therefore omits six work lines: site preparation and partitions, plaster, screed, first-fix electrics and plumbing, and glazing. Items rarely included are the gas boiler and radiators, interior doors, floor and wall finishes, the kitchen, bathroom fittings and tiling, sockets, switches, light fittings and air conditioning. On an 80 m² flat, heating alone costs ֏880,000. Handover specifications differ between developers and even between buildings in the same complex, so read the written finish specification annexed to the purchase contract before setting your budget.
For a typical two- or three-room apartment, a full renovation from a black frame usually takes about three to five months on site once the drawings and material choices are settled. For an 80 m² three-room flat with no add-ons, this calculator estimates about 13 weeks at Basic level, 15 at Comfort and 21 at Premium, or about 11 weeks from a white frame. A fitted kitchen or built-in joinery adds roughly another week, so the default view is one week longer. Add 15–20% for lead times and plan on four to six months from start to finish. Most delays come from late material decisions, lead times for custom kitchens and joinery, and building rules that restrict noisy work to weekday hours. Plan for that period in your cash flow because many buyers pay rent and a mortgage at the same time for several months.
Sometimes, but never automatically. Several Armenian banks offer a separate renovation or consumer loan alongside the mortgage, and some calculate the maximum mortgage from the appraised value of the finished apartment rather than the shell price, freeing up cash for the work. Conditions, rates and documentation requirements vary by bank, so ask before signing the purchase contract; restructuring afterwards is harder and usually costs more.
It usually raises the asking price, but rarely by the full amount spent. A neutral, well-executed mid-range finish tends to retain the most value because it appeals to more buyers who want to move in immediately, while highly personalised or luxury finishes recover the smallest share. For an apartment you intend to rent out, a durable and simple finish is generally the better financial choice because location and layout have far more effect on rent than finish quality.
It depends entirely on who provides the quote. VAT-registered construction companies add 20% VAT, which should appear as a separate line in the estimate, while smaller crews and individual contractors often work under the turnover-tax regime and quote a single cash figure with no VAT. A cheaper cash quote may also come without a written warranty or formal acceptance document, so consider the protection you would give up rather than treating the difference as a pure saving.
A general contractor charges a coordination margin, commonly shown as a percentage added to the trades' costs, in exchange for scheduling the work, sourcing materials and taking responsibility for defects. Managing the electrician, plumber, tiler and joiner yourself removes that margin, but takes your time and only works if you can visit the site regularly and resolve conflicts between trades quickly. Either way, insist on a written, room-by-room scope with quantities because nearly every renovation dispute concerns what was or was not included in the estimate.
Finishing a shell yourself is usually cheaper per square metre and gives you the layout and quality you want rather than someone else's choices. The trade-off is time, cash flow and risk: you manage the work, live somewhere else in the meantime, and bear any overrun. A finished apartment costs more up front but is move-in ready and can be mortgaged at its full value, which matters if you cannot fund the renovation from savings.
A common rule of thumb is 10–15% on top of the agreed estimate, or closer to 20% if you plan to move walls, relocate wet rooms or alter the risers. Overruns in new builds most often come from scope changes during the project, corrections to screed and plaster after the actual levels are measured, and changes in material prices between quotation and purchase. Keep the contingency as a separate, visible line rather than folding it into the estimate; this makes it much easier to resist scope creep.